Warehouse Fit Out
Our fitters completed this project within 4 days including the skim finish. A new client contacted Tru-Fix Interiors only 7 days before we started on site. The client needed new offices and storerooms building under a new mezzanine floor within a warehouse in Huddersfield. The walls needed to be 1 hour fire rated to protect staff in the event of a fire. The brief was simple we need the works completing with the next 2 weeks can this be done, our answer was yes, the fixers on this project worked long days to achieve the clients deadline, well done guys
#warehousefitout #Huddersfield #leedscontructioncompany #fireratedpartitionwalls #trufixinteriors #construction #mfceilingsleeds #interiorfitoutcompanyleeds #suspendedceilingsleeds #constructionindustry #studpartitions #drylining #leedssuspendedceilingcontractor #fullturnkeycontractor #shopfittingcompanyleeds #fireratedpartitionwalls #bespokelightingdetails #tapeandjointingcontratorsleeds #paintingcontratorsleeds #featurewallpaper #firewall